Who Pays for Data Centers
Home › Water

Data centers and water: the number under the number

Federal figures, direct and indirect, with the arithmetic shown · as of 2026-08-26

Most coverage of data-center water counts the water that goes through the building. That is the smaller number. The larger one is upstream, at the power plant: thermoelectric generation and hydroelectric reservoirs both lose water to evaporation, so every kilowatt-hour a data center buys carries water with it. Federal researchers put the upstream figure at roughly 12 times the on-site one.

That is why this site covers water at all. The electricity is the part we already track, state by state, and the electricity is where most of the water is.

What a data center's water actually costs, in water

Enter a size and utilization. The arithmetic is two published intensity factors applied to a load; it is not a measurement of any specific facility, and it does not know what cooling technology a given building uses.

701 GWh/yr
Electricity: 100 MW at 80% utilization.
69.4M gallons/yr
Direct water, evaporated in the building's own cooling, at the 0.375 L/kWh U.S. data-center average implied by LBNL's 2023 figures.
836.8M gallons/yr
Indirect water, evaporated at the power plants making that electricity, at LBNL's published 4.52 L/kWh for data-center electricity.
2,781 acre-feet/yr
Direct plus indirect combined, which is 0.37% of the 760,000 acre-feet Arizona gives up in 2027 under the federal Colorado River guidelines. That comparison, in full.

Worked example above: a 100 MW facility at 80% utilization draws 701 GWh a year, which carries 69.4 million gallons of direct and 836.8 million gallons of indirect water, or 2,781 acre-feet in total.

Reclaimed, non-potable and “zero water”

A single volume figure hides two things that matter as much as the volume: where the water came from, and what the cooling design gives up to avoid using it. A facility cooled on treated municipal effluent is not competing for drinking water the way one on potable supply is, and operators increasingly say so explicitly.

Waterless cooling is not water-free

The other half of the picture is a straight engineering tradeoff, and the federal report states it plainly:

The above discussion does not imply low site WUEs are necessarily good. In many cases, there are tradeoffs between low PUEs and low site WUEs. For example, water-cooled chillers and other evaporation-based cooling systems are generally more energy efficient than an air-cooled chiller or other waterless systems. While air-cooled chillers use no water, they use more energy.

Source: Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report

Evaporation is how a cooling tower sheds heat cheaply. Take the evaporation away and the heat has to be moved mechanically, which costs electricity, and on this site's own arithmetic electricity carries 4.52 liters of water per kilowatt-hour at the power plant. So a waterless design does not remove the water. It moves it from the local aquifer or utility to wherever the generation is, which may be another watershed entirely. The operators say the same thing about their own designs:

Where the tradeoff breaks even

Those two published intensities give a break-even. A facility on the U.S. average direct intensity of 0.375 L/kWh that switches to a waterless design saves that water on site, but adds 4.52 L/kWh of power-plant water on every extra kilowatt-hour the new cooling draws. The two cancel when the change raises total electricity use by about 8.3%. Below that, going waterless genuinely lowers total water consumption; above it, the facility is consuming more water than before, just somewhere else.

That figure is arithmetic on two LBNL numbers (0.375 ÷ 4.52), not a measured result, and it moves with the grid. LBNL notes that source water is "highly dependent on the source of electricity": on a grid with little thermoelectric or hydro generation the break-even is far higher, and on a thermoelectric-heavy grid it is lower. Neither Microsoft nor any other operator publishes the size of its own PUE increase, so this page cannot tell you which side of the line a given building falls on.

Why nobody can tell you what the plant down the road uses

There is no federal requirement that a data center publish its water use. What exists is a patchwork: company sustainability reports, which are voluntary and rarely broken out by site, and state or local filings, which exist only where a regulator requires them.

Every facility figure we can source →

Who pays, and where the fight is

Water is delivered by municipal utilities, so when a data center needs more than a city can supply, the upgrade is built by local government and recovered from local customers unless the developer funds it. Who pays for a data center's water → · what a kilowatt-hour costs in water, state by state →

The Colorado River is the sharpest version of this question in the United States, and it moved on August 21, 2026. Arizona, the Colorado River and the data centers →

Download the national figures (CSV) · Your state → · How data centers reach your bill →