Large-load tariff tracker

Who makes data centers pay - verified terms, as of 2026-08-12

A large-load tariff is a special rate class for very large electricity customers - in practice, data centers - that locks them into long contracts with minimum payments, so that if a project shrinks or leaves, the grid upgrades built for it are not stranded on everyone else's bills. The table below is free to cite and reuse with attribution; it is curated from public commission orders and verified reporting, dated 2026-08-12.

StateUtility / frameworkStatusThresholdMinimum takeTermDocket / source
AZAPS / statewide (ACC generic large-load docket)pending---ACC Docket No. E-00000A-25-0069
Arizona Corporation Commission
COXcel Energy (Public Service Co. of Colorado)pending≥50 MW-15 years (proposed)-
Colorado Sun
DEDelmarva Power & Lightpending≥25 MW--DE PSC Docket No. 25-0826
Delaware Public Service Commission
GAGeorgia Powerapproved
2025-01
>100 MW-up to 15 years (extended from prior 5-year contracts), with minimum billing requirements-
Georgia Public Service Commission
INIndiana Michigan Power (AEP)approved
2025-02
≥70 MW per facility, or 150 MW aggregated across a company-12 years minimum, starting after a ramp-up period of up to 5 years-
Utility Dive
KSEvergy Kansasapproved
2025-11
≥75 MWminimum monthly bill based on 80% of contract demand12 years minimum after a ramp-up of up to 5 years-
Utility Dive
MIConsumers Energyapproved
2025-11
≥100 MW80% of expected monthly demand15 years minimum, with a ramp period of up to 5 years-
Utility Dive
MNXcel Energy (very large customer class)approved
2026-05
≥100 MW new load; also 20-100 MW customers deemed 'system intensive'-15 years minimumMPUC Docket 25-289
Fresh Energy / MPUC
MOAmeren Missouriapproved
2025-11
≥75 MWminimum monthly demand charge of 80% of maximum requested electric demand12 years minimum, up to 17 years including an optional load-ramp period-
Ameren Missouri (approval release)
MOEvergy Missouriapproved
2025-11
≥75 MW (at monthly peak)---
St. Louis Public Radio
NCDuke Energy (Carolinas/Progress)settlement filed----
Environmental Defense Fund (Climate 411)
NJAll NJ electric utilities (statutory framework)enacted
2026-07
≥50 MW peak demand (or a lower threshold the BPU sets)financial guarantees covering at least 85% of requested service10 years minimumData Center Fair Share Act (S731/A796)
Office of the Governor of New Jersey
NVNV Energy (Clean Transition Tariff)approved
2025-05
----
Latitude Media
OHAEP Ohioapproved
2025-07
>25 MW85% of subscribed capacity12 years (8-year minimum after a load-ramp period of up to 4 years)PUCO Case No. 24-508-EL-ATA
Vorys (PUCO order analysis)
ORPortland General Electric (Schedule 96)approved
2026-05
>20 MW90% of contracted system capacity (minimum generation and transmission demand charges)10 years minimum, scaling to 30 years for loads of 220 MW or moreOPUC Docket UM 2377, Order No. 26-154
Oregon Public Utility Commission
ORPacific Power (PacifiCorp)approved---OPUC Docket UE 433 (2024 general rate case); updated data-center tariff pending in Docket UE 463
Oregon Public Utility Commission
PAAll PA electric distribution companies (PUC model tariff framework)approved
2026-05
>50 MW single customer or >100 MW aggregate--PA PUC Docket M-2025-3054271
Pennsylvania PUC
PAPPL Electric Utilitiesapproved
2026-06
≥50 MW at a single facility, or ≥75 MW aggregate among facilities served at ≥69 kV within a 10-mile radius-10 years minimum initial term, with a load-ramp schedule of up to 5 yearsPA PUC Docket R-2025-3057164
Pennsylvania PUC
TXAll ERCOT large loads (statutory framework)enacted
2025-06
≥75 MW--Texas Senate Bill 6 (2025)
Pillsbury Law
UTRocky Mountain Power (statutory framework)enacted
2025-03
≥100 MW expected within 5 years--Utah S.B. 132 (2025)
Latitude Media
VADominion Energy Virginia (GS-5)approved
2025-11
≥25 MW85% of contracted distribution and transmission demand; 60% of generation demand14 yearsSCC Case No. PUR-2025-00058
Virginia State Corporation Commission
WIWe Energies (Very Large Customer tariff)approved
2026-04
≥100 MW (lowered by the PSC from the proposed 500 MW)-15 years minimum (extended by the PSC from the proposed 10)PSCW Docket 6630-TE-113
Yale Clean Energy Forum

"Minimum take" = the share of contracted service a customer must pay for whether or not it uses it. Missing cells mean the term was not verified in a public source - not that it does not exist. The comprehensive academic database is NCCETC/SEPA's DELTa; this page is an independent curation of the most consequential frameworks with the terms inline and citable.