Georgia electricity prices - 16.36¢/kWh (June 2026)

Residential price, average bill, and the data-center story

8.4910.5712.6514.7316.812012201420162018202020222024202616.36
Georgia: average residential electricity price, ¢/kWh, monthly since 2010. Source: EIA Form 861M.
Free to reuse with credit. Please link to whopaysfordatacenters.com.
$71$114$158$201$24520122014201620182020202220242026$197
Georgia: average residential monthly bill (revenue ÷ customers), monthly. Source: EIA Form 861M.
Free to reuse with credit. Please link to whopaysfordatacenters.com.

Price by sector

Sector¢/kWh (June 2026)1-yr change
Residential16.36¢+2.5%
Commercial11.91¢−2.1%
Industrial8.86¢−4.2%

Data centers & Georgia's electric bills

On December 19, 2025, the Georgia Public Service Commission voted 5-0 to approve a stipulated agreement allowing Georgia Power to build 9,885 MW of new generation, mostly to serve data centers, with Georgia Power financially backstopping the projects in 2029-2031 beyond a base-rate freeze that runs through the end of 2028. PSC staff had earlier warned residential bills could rise about $20 per month if data-center revenue failed to materialize; the settlement's revenue guarantee was designed to address that risk. A state audit estimated Georgia's data-center sales-tax exemption cost $474.2 million in forgone state revenue in fiscal 2025.

Each item above is dated and linked to its primary source; entries are reviewed quarterly. See the large-load tariff tracker and the who-paid-what ledger for the cross-state picture.

Water

Electricity delivered in Georgia carries 8.29 liters of water per kilowatt-hour consumed at the power plants supplying it (1.52 L/kWh excluding hydropower reservoir evaporation), against a national average of 4.28. That is above the national figure, and it is a property of the grid here rather than of any one building: a data center drawing 100 GWh a year in Georgia accounts for about 219 million gallons of power-plant water before it cools anything. All states ranked →

A data center's water use is roughly twelve times larger once the water evaporated at its power plants is counted. The Colorado River arithmetic → · how the water numbers work →

All states ranked → · Download Georgia data (CSV) · Glossary