Who Pays for Data Centers
HomeStates › Arizona

Arizona electricity prices - 15.18¢/kWh (June 2026)

Residential price, average bill, and the data-center story

9.1810.9912.8014.6116.422012201420162018202020222024202615.18
Arizona: average residential electricity price, ¢/kWh, monthly since 2010. Source: EIA Form 861M.
Free to reuse with credit. Please link to whopaysfordatacenters.com.
$59$116$173$230$28620122014201620182020202220242026$219
Arizona: average residential monthly bill (revenue ÷ customers), monthly. Source: EIA Form 861M.
Free to reuse with credit. Please link to whopaysfordatacenters.com.

Price by sector

Sector¢/kWh (June 2026)1-yr change
Residential15.18¢−0.3%
Commercial12.47¢−3.6%
Industrial7.73¢−6.4%

Data centers & Arizona's electric bills

Arizona's two largest investor-owned utilities have rate cases pending at the Arizona Corporation Commission: APS has proposed a roughly 14% increase (about $20 per month for the average residential customer, and up to 45% for data centers) plus a formula rate plan allowing annual adjustments, and Tucson Electric Power is seeking a 14% increase. Attorney General Kris Mayes has intervened in both, filing expert testimony that TEP's increase could be cut to 4%. Decisions are expected toward the end of 2026.

Each item above is dated and linked to its primary source; entries are reviewed quarterly. See the large-load tariff tracker and the who-paid-what ledger for the cross-state picture.

Water

Electricity delivered in Arizona carries 12.72 liters of water per kilowatt-hour consumed at the power plants supplying it (1.50 L/kWh excluding hydropower reservoir evaporation), against a national average of 4.28. That is above the national figure, and it is a property of the grid here rather than of any one building: a data center drawing 100 GWh a year in Arizona accounts for about 336.1 million gallons of power-plant water before it cools anything. All states ranked →

Arizona's Colorado River apportionment falls to 2.04 million acre-feet in 2027 and 2028, a reduction of 760,000 acre-feet, the deepest cut of any state under the federal guidelines issued August 21, 2026. Data-center water use is a small share of that arithmetic and a fast-growing one: Phoenix data centers were estimated at around 385 million gallons a year, with projections near 3.8 billion.

A data center's water use is roughly twelve times larger once the water evaporated at its power plants is counted. The Colorado River arithmetic → · how the water numbers work →